Etchings Cellular Facility; Zap 96-051w1, Log No. 96-14-034
2 Documents in Project
Summary
SCH Number
2001111015
Lead Agency
San Diego County
Document Title
Etchings Cellular Facility; Zap 96-051w1, Log No. 96-14-034
Document Type
NOD - Notice of Determination
Received
Posted
3/5/2002
Present Land Use
The proposed project is subject to the Regional Category EDA, Estate Development Area and General Plan Land Use Designation 18, Multiple Rural Use. The project is subject to the policies of the Lakeside Community Plan. The current zone is A70, Limited Agricultural Land Use Regulation, which permits a Minor Impact Utility with the issuance of a Minor Use Permit pursuant to the Zoning Ordinance Section 2704b.
Document Description
The project proposes a modification of an existing telecommunications facility operated by Pacific Bell Services. Nextel proposes to replace the existing wood monopole with a new monopole of the same height. The new monopole will be a co-location site for both companies. The additional Nextel antennas measure 1 foot wide by 4 feet in length. Eight of the new panel antennas will be added to the two existing PacBell omni antennas. Nextel also proposes a new enclosed equipment cabinet, measuring 10 feet by 20 feet.
Contact Information
Name
Amy C. Mathews
Agency Name
San Diego County
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Diego
Counties
San Diego
Cross Streets
Highway 67 & Hi Hopes Drive
Total Acres
5.93
Parcel #
375-170-18-00
State Highways
Hwy 67
Railways
None
Airports
None
Waterways
None
Base
S.B.B.M.
Notice of Determination
Approving Agency
County of San Diego Zoning Administrator
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.