Richmond Campus Phase III

4 Documents in Project

Summary

SCH Number
2001032085
Lead Agency
California Department of Public Health (CDPH)
Document Title
Richmond Campus Phase III
Document Type
NOD - Notice of Determination
Received
Posted
9/27/2001
Present Land Use
The site is part of the existing Richmond Campus. The existing campus facility generally corresponds to land use designations and development goals and policies applicable to industrial/office flex uses in this area of Richmond, as set forth in the Richmond General Plan, the Knox Freeway/Cutting Boulevard Corridor Specific Plan and the Richmond Zoning Ordinance.
Document Description
The proposed site of the Richmond Phase III Office Building Project would be located on approximately nine acres within the southern portion of the State owned laboratory campus. Presently under construction, development of 20 acres of the 29 acre Richmond Campus is currently underway. The present facilities represent the implementation of Phase I and Phase II of an ongoing project to consolidate Department of Health Services facilities, previously located in several East San Francisco Bay Area communities. The first two phases include four laboratory wings, three office wings, and a central services building. Phase III would be a three-story office structure, approximately 200,000 GSF. The Phase III development would include tie-ins to all existing site development features of Phase I and II. Additional parking for 600 vehicles would be constructed along with new landscaping.

Contact Information

Name
Paul Helwer
Agency Name
Department of Health Services
Contact Types
Lead/Public Agency

Location

Cities
Richmond
Counties
Contra Costa
Cross Streets
Marina Bay Parkway/Meeker Avenue
Total Acres
9
State Highways
I-580, I-80
Waterways
San Francisco Bay

Notice of Determination

Approving Agency
Department of Health Services
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print