Petition to Increase Simple-Cycle Operating Hours for the Sunrise Power Project
8 Documents in Project
Summary
SCH Number
2000129017
Lead Agency
California Energy Commission
Document Title
Petition to Increase Simple-Cycle Operating Hours for the Sunrise Power Project
Document Type
NOD - Notice of Determination
Received
Posted
1/8/2002
Document Description
Post-certification project change: Clarification of potential conflicts between air quality conditions of certification AQ-10, -14 & -15 regarding the definition of startup period and Continuous Emission Monitoring (CEM).
Contact Information
Name
Nancy Tronaas
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency
Phone
Email
Location
Counties
Kern
Notice of Determination
Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.