Pico Canyon Elementary School
4 Documents in Project
Summary
SCH Number
2000081091
Lead Agency
Newhall School District
Document Title
Pico Canyon Elementary School
Document Type
NOD - Notice of Determination
Received
Posted
9/29/2000
Document Description
Acquisition of approximately 8.4 acres of undeveloped land for the construction and operation of the proposed Pico Canyon Elementary School. The project contemplates the construction of classroom facilities organized in single-story and two-story buildings with covered walkways and fencing. Facilities to be constructed include classrooms for elementary and kindergarten students, day care facilities, pre-school, an administration and library building, music room, gymnasium, kitchen/cafeteria, and multi-purpose room. The project contemplates parking facilities for up to 120 vehicles, a segregated bus-loading and drop-off area. Athletic play courts include hardscape and turf playfields. Lighting includes low level security lighting, signage lighting and illumination of the surface parking lot and associated pedestrian areas.
Contact Information
Name
Dr. Marc Winger
Agency Name
Newhall School District
Contact Types
Lead/Public Agency
Phone
Location
Counties
Los Angeles
Cross Streets
Stevenson Ranch Parkway and Pico Canyon Road
Total Acres
8.4
Schools
Newhall School District
Township
4N
Range
16W
Section
32
Base
SB
Other Location Info
Stevenson Ranch, east of the intersection of Stevenson Ranch Parkway and Pico Canyon Road
Notice of Determination
Approving Agency
Newhall School District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.