Walnut-Hilmar Transmission Line Project

2 Documents in Project

Summary

SCH Number
2000062001
Lead Agency
Turlock Irrigation District
Document Title
Walnut-Hilmar Transmission Line Project
Document Type
NEG - Negative Declaration
Received
Present Land Use
General Agriculture, Industrial, Zoning A2-40, A-1, I
Document Description
TID plans to expand the existing Walnut Substation by adding a 230-kV/115-kv transformer, 115-kv and 69-kv circuit breakers, and related equipment. TID also plans to add 7.9 miles of 115-kv transmission lines along Washington Road, Harding Road, and Lander Avenue.

Contact Information

Name
Randy Baysinger
Agency Name
Turlock Irrigation District
Contact Types
Lead/Public Agency

Location

Cities
Turlock, Turlock, Hilmar
Counties
Merced, Stanislaus
Cross Streets
Washington Road, West Main
Total Acres
1.4
Parcel #
044-01-10
State Highways
165
Railways
Union Pacific
Airports
Turlock Airpark
Schools
Turlock, Hilmar
Waterways
Laterals No. 5, 6, 7
Township
5S
Range
10E
Section
19
Base
MDBM

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Conservation (DOC), California Department of Fish and Wildlife, Central Region 4 (CDFW), California Department of Transportation, District 10 (DOT), California Energy Commission, California Native American Heritage Commission (NAHC), California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), California State Lands Commission (SLC), Caltrans, Division of Aeronautics, Central Valley Flood Protection Board, Department of Toxic Substances Control, Office of Historic Preservation, Resources Agency, California Regional Water Quality Control Board, Central Valley Fresno Region 5 (RWQCB)
State Reviewing Agency Comments
California Regional Water Quality Control Board, Central Valley Fresno Region 5 (RWQCB)
Development Types
Power:Electric Transmission Lines (Transformer)(Megawatts 115-kv), Power:Other Power Type (Transmission lines)(Megawatts 115-kv)
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Cultural Resources, Cumulative Effects, Drainage/Absorption, Flood Plain/Flooding, Geology/Soils, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Schools/Universities, Transportation, Wildfire, Wildlife

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print