Sutter Medical Center Cardiac Catheterization/MRI Facility
2 Documents in Project
Summary
SCH Number
2000052029
Lead Agency
Sonoma County
Document Title
Sutter Medical Center Cardiac Catheterization/MRI Facility
Document Type
NOD - Notice of Determination
Received
Posted
6/29/2000
Present Land Use
Present Land Use: Hospital
Zoning: PB (Medical Center)
General Plan Designation: Public/Institutional.
Document Description
Sonoma County plans to allow Sutter Medical Center of Santa Rosa to construct a 6,541 square foot modular building to house a new Cardiac Catheterization and Magnetic Resonance Imaging facility. The single story building will be located in the paved parking lot behind the four story wing of the hospital. It will most likely be connected to the main building by a fully enclosed corridor which will be built on-site. The paving in the parking lot will be removed, graded and a concrete slab foundation will be poured in place, with modifications to storm drain facilities / utilities. A retaining wall with a handrail above will be built to separate the new building from the relocated fire access road and the existing concrete walkway to the helipad.
Contact Information
Name
Paula Stamp
Agency Name
Sonoma County General Services Department
Contact Types
Lead/Public Agency
Phone
Location
Cities
Santa Rosa
Counties
Sonoma
Cross Streets
Chanate Road
Zip
95404
Total Acres
2
Parcel #
171-130-038
Railways
NWPRR
Schools
Steele Lane, Fremont, Proctor Terrace Elementary, Santa Rosa
Waterways
Paulin Creek, Santa Rosa Creek
Township
10N
Range
7W
Section
Rancho
Base
MtDiablo
Other Information
Schools Continued: Junoir High
Section Continued: Los Guilicos
Notice of Determination
Approving Agency
Sonoma County Board of Supervisors
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A