Application to Appropriate Water Petitions for Extension of Time and Request for Licenses
5 Documents in Project
Summary
SCH Number
2000032044
Lead Agency
State Water Resources Control Board
Document Title
Application to Appropriate Water Petitions for Extension of Time and Request for Licenses
Document Type
NOD - Notice of Determination
Received
Posted
12/5/2001
Present Land Use
Resource and Rural Development
Document Description
Geysers Power Company (Geysers) proposes to divert up to 22 cubic feet per second (cfs) of water from Big Sulphur Creek at its BSC-3 Extraction Facility (BSC-2 facility) in accordance with the conditions in its water rights permit (No. 21066) ("permit" or "water rights permit"). The BSC-2 facility is an existing screened diversion located on Big Sulphur Creek in the southwest corner 1/4 of Section 28, Township 11 North, Range 8 West. The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement Number R3-2001-0805 pursuant to Section 1603 of the Fish and Game Code to the project operator, John Farison - Geysers Power Company, LLC.
Contact Information
Name
Gene Geary
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Sonoma
Cross Streets
Geysers Road and Geysers Resort Road
Total Acres
9000
Parcel #
141-04-01, 05, 06, 07, & 24
Waterways
Big Sulphur Creek
Township
10-12N
Range
8,9W
Base
MD
Other Location Info
The Geyser
Other Information
township: 10, 11, & 12N
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A