City of Lincoln Wastewater Treatment and Reclamation Facility
Document Type
NOD - Notice of Determination
Received
Posted
8/10/2001
Document Description
The California Department of Fish and Game is executing a Lake or Streambed Alteration Agreement number R2-2001-302 pursuant to Section 1601 of the Fish and Game Code to the project applicant, City of Lincoln.
This agreement pertains to the construction of two storm drain outfall structures into a tributary of Orchard Creek. The first outfall is located east of and adjacent to Fiddement Road and outfalls into Orchard Creek. Both outfalls will allow storm water runoff to enter into existing drainage courses from concrete lined "V" ditches without eroding ditch/stream banks. Construction of the outfalls requires the placement of native river cobble on the banks of both the ditch and Orchard Creek to protect against erosion.
Contact Information
Name
Cathie Vouchilas
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Lincoln
Counties
Placer
Cross Streets
MOORE RD, FIDDYMENT RD.
Total Acres
780+-
Parcel #
021-280-002 plus others
State Highways
65
Railways
Southern Pacific
Waterways
Auburn Ravine, Ingram Slough, Orchard Creek
Township
12N
Section
25,30
Base
MDM
Other Location Info
Tributary to Orchard Creek.
Notice of Determination
Approving Agency
Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.