Physical Sciences Building
3 Documents in Project
Summary
SCH Number
1998112054
Lead Agency
University of California Santa Cruz
Document Title
Physical Sciences Building
Document Type
NOD - Notice of Determination
Received
Posted
1/21/2000
Document Description
The proposed project is the construction of a new four-and five-story (approximately 78,500 assignable square feet [asf]) Physical Sciences Building on the site of an existing parking lot just southeast of the intersection of McLaughlin Drive and Steinhart Way in the central Santa Cruz campus. The project would provide classroom space, teaching laboratory space, computer laboratory space, research and research support space for Chemistry, Environmental Toxicology, and Engineering programs. In addition to the proposed building, the project would provide new and improved pedestrian paths, a loading dock and loading dock access road, a shuttle stop, emergency access to science hill, disabled parking, connections to existing utilities, storm drainage facilities, a new or modified cooling tower, and landscaping. The building would be constructed on a 2.3-acre building site located on and adjacent to existing parking lots #113 and #114 on the central campus; the drainage improvements would be constructed on a 0.21-acre site located in a tributary of Moore Creek, southwest of the building site; and the cooling tower would be constructed on a 0.24-acre site located northeast of the designated "Campus Core" in the UCSC 1988 Long Range Development Plan (LRDP); the cooling tower site is designated "Campus and Community Support." The primary objective of the project is to remedy existing and anticipated space deficiencies and functional inadequacies in campus academic buildings.
Contact Information
Name
ANN BERTKEN
Agency Name
UC SANTA CRUZ
Contact Types
Lead/Public Agency
Location
Cities
Santa Cruz
Counties
Santa Cruz
Cross Streets
MCLAUGHLIN DRIVE AND STEINHART WAY
Schools
UC SANTA CRUZ
Notice of Determination
Approving Agency
N/A
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.