Concurrence in the Issuance of a Revised Solid Wast Facility Permit (SWFP No. No 42-AA-0015) Tajiguas Sanitary Landfill
9 Documents in Project
Summary
SCH Number
1998041003
Lead Agency
Livermore Valley Joint Unified School District
Document Title
Concurrence in the Issuance of a Revised Solid Wast Facility Permit (SWFP No. No 42-AA-0015) Tajiguas Sanitary Landfill
Document Type
NOD - Notice of Determination
Received
Posted
4/24/2003
Present Land Use
Landfill and borrow area; AG-II-100; AG-II
Landfill; northern portion: AG-II-100; AG-II
southern portion: AG-II-320; Local Coastal Plan AG-II
Document Description
Revise the Solid Waste Facility Permit to increase permitted vehicles from 128 vehicles per day to 184 vehicles per day, increase the disposal area from 78 acres to 118 acres, increase the disposal capacity from 15.1 million cubic yards to 23.2 million cubic yards, change hours of operation, change permitted maximum elevation from 500 feet above mean sea level to 620 feet above mean sea level, change closure date from 2006 to 2020 and incorporation of a projection known as the Southeast Corner Modification.
Contact Information
Name
Williy Jenkins
Agency Name
California Integrated Waste Management Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Santa Barbara
Counties
Santa Barbara
Cross Streets
Highway 101
Total Acres
497
Parcel #
081-150-019, 081-150-026
State Highways
101
Railways
Southern Pacific
Waterways
Arroyo Quemado, Canada de la Pila, Arroyo Hondo
Township
5N
Range
31W
Base
SBBM
Notice of Determination
Approving Agency
California Integrated Waste Management Board
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.