Boron Sanitary Landfill Permit Revision Project

3 Documents in Project

Summary

SCH Number
1997081087
Lead Agency
Kern County
Document Title
Boron Sanitary Landfill Permit Revision Project
Document Type
NOD - Notice of Determination
Received
Posted
6/2/2014
Present Land Use
Class III Landfill & Vacant, Open Space / A-1 (Lim Ag) & R-1 (Low-Den Res) / 3.4 (Solid Waste Disp), 8.3 (Ext Ag) & 8.5 (Res Mgmt)
Document Description
1. Increase the permitted facility boundary to 120.21 acres to include adjacent property acquired as a buffer to the active lanfill. Also for use as a source of cover soil and ultimately converted to a drainage basin. 2. Adjust the disposal footprint by 0.10 acres as a result of a waste study, which determined the actual disposal footprint to be 14.1 acres rather than the currently permitted 14 acres; 3. Increase the maximum days and hours of operation of seven days per week, from no earlier than 6:00 a.m. (currently 7:00 a.m.) to no later than 5:00 p.m. (excluding county holidays); 4. Increase in the permitted disposal capacity from 1,002,819 to 1,057,000 cubic yards; and, 5. Changes in estimated closure date from 2037 to 2048

Contact Information

Name
Christine Karl
Agency Name
CalRecycle
Contact Types
Lead/Public Agency

Location

Cities
BORON
Counties
Kern
Cross Streets
Boron Avenue and Twenty Mule Team Road
Zip
93516
Total Acres
121.21
Parcel #
244-010-07; -14, -23, -35
State Highways
Hwy 58
Railways
BNSF
Airports
Edwards AFB
Schools
Boron Junior Senior HS
Waterways
No
Township
10N
Range
7W
Section
5/6
Base
SBB&M
Other Location Info
Boron

Notice of Determination

Approving Agency
CalRecycle
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes