66KV SUBSTATION PROJECT
Summary
SCH Number
1996104369
Lead Agency
Regents of the University of California
Document Title
66KV SUBSTATION PROJECT
Document Type
NOD - Notice of Determination
Received
Posted
7/29/1996
Document Description
CONSTRUCTION AND OPERATION OF A NEW 66 KILOVOLT ELECTRICAL SUBSTATION LOCATED ON THE MAIN CAMPUS OF UC SANTA BARBARA.
Contact Information
Name
AERYN RICHMONDE
Agency Name
UNIVERSITY OF CALIFORNIA, SANTA BARBARA
Contact Types
Lead/Public Agency
Phone
Location
Cities
UC SANTA BARBARA
Counties
Santa Barbara
Notice of Determination
Approving Agency
N/A
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A