Black Rascal Flood Control Project

3 Documents in Project

Summary

SCH Number
2017021015
Lead Agency
Merced County
Document Title
Black Rascal Flood Control Project
Document Type
NOD - Notice of Determination
Received
Posted
1/16/2018
Present Land Use
General Agriculture (A-1)
Document Description
Merced County is proposing to implement a flood control project immediately upstream of the Black Rascal Creek Diversion Channel. The proposed detention basin and wetland area would temporarily store flow during periods of heavy rain and limit flow in the Diversion Channel to 3,000 cfs. The proposed project would include a perimeter levee surrounding a 300-acre inundation area, to accommodate up to 2,800 acre-feet of water during a 200-year storm event, and an internal levee to protect agricultural land within the basin during more frequent storms, 50 year event. The detention basin outlet would also include a series of reinforced concrete box culverts to limit flows in the diversion channel.

Contact Information

Name
Mike Walejko
Agency Name
Merced County
Contact Types
Lead/Public Agency

Location

Cities
Merced
Counties
Merced
Cross Streets
Yosemite/North Arboleda Dr.
Zip
95340
Total Acres
600
Parcel #
060-060-004/006/007; 053-070-010
Schools
UC Merced
Waterways
Black Rascal Creek, Bear Creek, Burns Creek
Township
7S
Range
14E
Section
12

Notice of Determination

Approving Agency
Merced County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print