Port of Hueneme Berth Deepening and Wharf Improvement Project
3 Documents in Project
Summary
SCH Number
2017011049
Lead Agency
Oxnard Harbor District
Document Title
Port of Hueneme Berth Deepening and Wharf Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
3/20/2017
Present Land Use
surrounded by Port Related uses to the west and south and Naval Construction Battalion Center to the north and east
Document Description
The proposed project's berth deepening effort would include dredging activities to deepen Berths 1 and 2 along Wharf 1 to approximately 40 feet MLLW, to provide deep draft vessel continuity from the harbor, through the channel and to Berths 1 and 2 along Wharf 1. Dredged sediment would be placed using one of two options. Under Option 1, dredged sediment found to meet applicable physical and chemical thresholds would be placed on Hueneme Beach for beach nourishment or in the near-shore zone adjacent to Hueneme Beach. Under option 2, the USACE would over dredge portions of Channel A to a depth of approximately 48 feet MLLW to create trenches for wharf sediment disposal.
Contact Information
Name
Christina Birdsey
Agency Name
Oxnard Harbor District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Port Hueneme
Counties
Ventura
Cross Streets
East Port Hueneme Rd and Market St
Zip
93044
Total Acres
55.01
Railways
VC Railroad comp
Schools
Port Hueneme ES
Waterways
Pacific Ocean
Notice of Determination
Approving Agency
Oxnard Harbor District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes