Horseshoe Bend Levee Improvement Project (Lake or Streambed Alteration Agreement No. 1600-2017-0190-R3)

5 Documents in Project

Summary

SCH Number
2016112018
Lead Agency
Bethel Island Municipal Improvement District (BIMID)
Document Title
Horseshoe Bend Levee Improvement Project (Lake or Streambed Alteration Agreement No. 1600-2017-0190-R3)
Document Type
NOD - Notice of Determination
Received
Posted
8/28/2017
Present Land Use
Levee site/contra costa county F:1 Recreational district/ contra costa county: AL, SH, CR, PR, OS
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2017-0190-R3, pursuant to section 1602 of the Fish and Game Code to the project Applicant, L. Jeff Butzlaff, Bethel Island Municipal Improvement District (BIMID). BIMID will improve the levee to Bulletin 192-82 standards with a minimum landside slope of 5H:1V, widening the levee crest to a minimum of 22 feet, placing class 2 aggregate base on the levee crest in creation of an all weather road, constructing a clay cutoff wall, installing a blanket drain, or placing sheet piles in order to create and plant a 15 foot waterside bench at station 155+00 to 165+00, and installing new o enhancing existing riprap at station 130+00 to 180+00 as needed.

Contact Information

Name
Brianne O'Rourke
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Oakley
Counties
Contra Costa
Cross Streets
Bethel Island Rd
Zip
94511
Total Acres
105
Parcel #
multiple
Waterways
Taylor Slough, Piper Slough
Base
MD
Other Location Info
Bethel Island

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.