Linde Ambiguity Farm Trust Water Diversion Pond and Stream Crossings Project (Lake or Streambed Alteration Agreement No. 1600-2019-0698-R1)
549 Documents in Project
Summary
SCH Number
2015102005
Lead Agency
Humboldt County
Document Title
Linde Ambiguity Farm Trust Water Diversion Pond and Stream Crossings Project (Lake or Streambed Alteration Agreement No. 1600-2019-0698-R1)
Document Type
NOD - Notice of Determination
Received
Posted
12/11/2020
Document Description
The project is limited to 15 encroachments on unnamed tributaries to Squaw Creek. Two
encroachments are for water diversion for domestic use and irrigation. Work for the water diversion will include use and
maintenance of the water diversion infrastructure. The 13 other encroachments are to replace or maintain culverts and a
pond spillway. Work for these encroachments will include some or all of the following: excavation, culvert removal and/or
replacement, backfilling and compaction of fill, and rock armoring as necessary to minimize erosion.
Contact Information
Name
Ryan Bourque
Agency Name
Department of Fish and Wildlife
Contact Types
Lead/Public Agency
Address
Phone
Name
Agency Name
Michael Linde
Contact Types
Project Applicant
Location
Cities
Garberville
Counties
Humboldt
Regions
Northern California
Other Location Info
The project to be completed is located within Squaw Creek watershed,
approximately 4.92 miles east southeast of the town of Garberville, County of Humboldt, State of California. The project is
located in Section 27, T4S, R4E, Humboldt Base and Meridian; in the Harris U.S. Geological Survey 7.5-minute
quadrangle; Assessor’s Parcel Number 223-011-009 and 223-011-007; latitude 40.088388 N and longitude -123.70331 W
at the parcels center.
Notice of Determination
Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No