Phase 1 Replacement (SAA 1600-2014-0023-R2)

5 Documents in Project

Summary

SCH Number
2013092055
Lead Agency
City of Roseville
Document Title
Phase 1 Replacement (SAA 1600-2014-0023-R2)
Document Type
NOD - Notice of Determination
Received
Posted
4/21/2014
Present Land Use
Various
Document Description
The California Department of Fish and Wildlife is executing Lake or Streambed Alteration Agreement number 1600-2014-0023-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, Pacific Gas and Electric Company. The project is limited to the installation of new 16 inch gas pipeline to replace approximately 3,500 feet of existing outdated pipeline. Installation will be implemented via Horizontal Directional Drill (HDD). The HDD will cross beneath 2 watercourses and will include 2 staging areas of approximately 250 square feet to accommodate the drilling rig, water and slurry tanker, pipe laydown and entry and exit holes. The staging areas will be outside of riparian areas and the pipeline will be installed under the watercourses at a depth of 20-60 feet. Additionally, all vegetation within a 10 foot radius of the new gas pipeline will be trimmed or removed to ensure proper installation and line of sight over the pipeline for immediate and future pipeline inspection activities. This will include the removal of approximately 50 trees and saplings (oak, cottonwood, ash, etc.). Once the pipeline has been installed and connected to the existing gas line, it will be hydro-tested and placed in service. All areas will be restored to pre-existing conditions and the old pipeline will be abandoned in place unless it poses a hazard.

Contact Information

Name
JB Garcia
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Location

Cities
Roseville
Counties
Placer
Cross Streets
Blue Oaks Boulevard and Baseline Road
Zip
95747
Total Acres
32
State Highways
SR 65
Railways
UPRR
Schools
Various
Waterways
Dry Creek

Notice of Determination

Approving Agency
Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.