Irwindale Materials Recovery Facility and Transfer Station Project

9 Documents in Project

Summary

SCH Number
2013051029
Lead Agency
City of Irwindale
Document Title
Irwindale Materials Recovery Facility and Transfer Station Project
Document Type
NOD - Notice of Determination
Received
Posted
6/9/2016
Present Land Use
Vacant and disturbed / Heavy Manufacturing / Commercial
Document Description
The Irwindale Materials Recovery Facility and Transfer Station Project (MRF/TS) includes the development and operation of a materials recovery facility and transfer station, and convenience store/fueling station. The Proposed Project site is approx. 17.22 acres (APN 8535-001-911). The MRF/TS consists of a fully enclosed building with the interior designed to provide separate areas to receive, process, and transfer mixed municipal solid waste (MSW), green waste, construction and demolition (C&D) materials, and waste hauled in by self-haulers. The MRF/TS facility would be designed to receive, process and transfer up to a maximum of 6,000 tons per day (tpd). Hazardous wastes are prohibited at the MRF/TS. The fueling facility/convenience store would be separate structure located in the southeastern portion of the site adjacent to Arrow Highway and includes a fueling island with pump canopy, convenience store, and parking for customers.

Contact Information

Name
Gustavo Romo
Agency Name
City of Irwindale
Contact Types
Lead/Public Agency

Location

Cities
Baldwin Park, Irwindale
Counties
Los Angeles
Cross Streets
NW corner of Live Oak Avenue and Arrow Highway
Zip
91706
Total Acres
17
Parcel #
8535-001-911
State Highways
I-605 and 210
Railways
SPRR
Airports
No
Schools
Heath, Landis, Geddes
Waterways
San Gabriel River
Township
1S
Range
10W
Section
6
Base
SBB&M

Notice of Determination

Approving Agency
City of Irwindale
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print