California High Speed Train - Fresno to Bakersfield Permitting Packages 1.a and 1.b
75 Documents in Project
Summary
SCH Number
2009091126
Lead Agency
California High Speed Rail Authority
Document Title
California High Speed Train - Fresno to Bakersfield Permitting Packages 1.a and 1.b
Document Type
NOD - Notice of Determination
Received
Posted
8/10/2017
Present Land Use
Various (urban[industrial, commercial and residential], rural residential, agricultural, and undeveloped)
Document Description
This is an amendment of the regional certification. The project will construct approx. 87 miles of the overall HST project. The project includes the HST tracks, structures, stations, traction power substations, maintenance facilities, and train vehicles. The HST would use four different track types: at grade, elevated by either a structure or on a retained fill platform, and below-grade tracks in a retained cut. The type of bridges that might be built includes full channel spans, large box culverts, or for some larger river crossing's, piers within the ordinary high-water channel.
Contact Information
Name
Cliff Harvey
Agency Name
SWRCB
Contact Types
Lead/Public Agency
Phone
Location
Cities
Fresno, Madera
Counties
Fresno, Kern, Kings, Tulare
Zip
various
Total Acres
~114
Parcel #
various
State Highways
Hwy 43, others
Railways
UPRR, BNSF, SJVRR
Airports
Several Local Airports
Schools
Multiple
Waterways
Kings, Tule, & Kern Rivers; Cross & Poso Creeks
Township
variou
Range
variou
Section
variou
Base
various
Notice of Determination
Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes