Water Reclamation Facility #2 - Tertiary Filtration Project (Project) Clean Water State Revolving Fund (CWSRF) No. C-06-7834-110
6 Documents in Project
Summary
SCH Number
2008091085
Lead Agency
City of Corona
Document Title
Water Reclamation Facility #2 - Tertiary Filtration Project (Project) Clean Water State Revolving Fund (CWSRF) No. C-06-7834-110
Document Type
NOD - Notice of Determination
Received
Posted
3/14/2014
Present Land Use
Utility
Document Description
The Project includes the following construction activities:
Filter feed pump station and wet well
Reinforced concrete filter structure consisting of: Flocculation basin with mixer. Dual-media sand and anthracite filter with four filter beds and filter underdrain system. Backwash supply storage tank. Backwash wastewater equalization tank.
Backwash water supply pump station
Backwash wastewater pump station
Blowers and air piping for an automated backwash air scour system
Emergency diesel-engine drive generator
Chemical (Sodium Hypochlorite and Coagulant) storage and feed system with chemical spill containment and shade cover
Chlorine contact basin (CCB) splitter box
Various secondary effluent, backwash water, treated water, and overflow yard piping
Site drainage improvements to provide stormwater retention
Motor controls, switchgear, electrical, and supervisory control and data acquisition (SCADA) improvements.
Contact Information
Name
Christine Day
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Corona
Counties
Riverside
Cross Streets
E Harrison St and Le Roy Drive
Zip
92879
Total Acres
8
Parcel #
1193000071
State Highways
SR 91, I-15
Railways
BNSF
Schools
Corona-Norco USD
Waterways
Temescal Creek
Township
3S
Range
6W
Section
30
Base
SBB&M
Notice of Determination
Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.