La Paz Plaza

3 Documents in Project

Summary

SCH Number
2005021122
Lead Agency
City of Mission Viejo
Document Title
La Paz Plaza
Document Type
NOD - Notice of Determination
Received
Posted
4/18/2005
Present Land Use
Office Professional / Office/Retail
Document Description
The proposed La Paz Plaza project is a two-phase project; to renovate portions of the existing parking lot of the existing La Paz Plaza, and to construct a new two-story, 6,000 square foot building. In addition, a new parking lot containing 79 parking spaces will be constructed to accommodate the new office building. Each phase of the project will be able to proceed forward independent of the other phase. The project is a 5.6 acre site, however, the bulk of the new improvements will occur on the 2.2 acre parcel. This will consist of the new building and parking facilities located to the west of the existing office and retail center. In order to develop the site it will be necessary to import fill (dirt) earth material. In addition a paved ramp will be constructed to provide access to the new parking lot. Grading of the site will remove some of the eucalyptus trees while a number will be retained as part of the overall landscaping of the site. Grading for the new parking lot will also encroach into the existing La Paz Channel located immediately adjacent to the west side of the project. Re-grading of a portion of the existing embankment will be completed and be re-landscaped as part of the project plan.

Contact Information

Name
Elaine Lister
Agency Name
City of Mission Viejo
Contact Types
Lead/Public Agency

Location

Cities
Mission Viejo
Counties
Orange
Cross Streets
La Paz Road / Chrisanta
Zip
92691
State Highways
5
Railways
OCTA Metrolink
Schools
Mission Viejo High School
Waterways
La Paz Channel

Notice of Determination

Approving Agency
City of Mission Viejo, Planning and Transportation Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print