Pacific Rail Metal Shredding Operation
10 Documents in Project
Summary
SCH Number
2002111002
Lead Agency
City of Colton
Document Title
Pacific Rail Metal Shredding Operation
Document Type
NOD - Notice of Determination
Received
Posted
10/15/2004
Present Land Use
Heavy Industrial
Heavy Industrial (M2)
Heavy Industrial
Document Description
Project applicant, Pacific Rail Industries, proposes to amend their conditional use permit in order to allow the 1) installation and operation of a metal shredding operation as an expansion of a scrap metal facility; and 2) an increase in the volume of transloading (transfer of goods from rail car to truck for distribution) on the project site. The metal shredder would be relocated from an existing facility in Carson to the City of Colton where it would shred raw metal sources (car bodies, appliances, etc.) and separate metal and non-metal by physical and chemical means. Transloading would increase from 25,100 tons to 37,620 tons per month (approximately 50%).
Contact Information
Name
Andres L. Soto
Agency Name
City of Colton
Contact Types
Lead/Public Agency
Phone
Location
Cities
Colton
Counties
San Bernardino
Cross Streets
"M" Street, Mount Vernon Avenue
Zip
92324
State Highways
I-10, I-215
Railways
Union Pacific
Schools
Wilson, Colton, Lincoln
Waterways
Santa Ana River, local aqueducts
Township
1S
Range
4W
Notice of Determination
Approving Agency
City of Colton
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.