Elliot Field Station Structural Engineering Field Test Laboratory

2 Documents in Project

Summary

SCH Number
2002051115
Lead Agency
University of California San Diego
Document Title
Elliot Field Station Structural Engineering Field Test Laboratory
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2002
Present Land Use
University use
Document Description
Project would be constructed in two phases of development. The first phase would consist of the bridge abutment testing operation to observe soil foundation structural interaction. This phase would also include site grading, creation of an open storage area, and the construction of new access to the site from the Elliott Field Station main access road. A temporary trailer and generator will be placed on the site to support this research until Phase II is implemented. The second phase would consist of development of a high performance outdoor shake table and high energy impact simulator to be used for seismic and materials testing. Phase II would also include the construction of one or two buildings with a total size of approximately 4,000 gsf to house office space/ control room and power supply equipment, as well as utility installation.

Contact Information

Name
Catherin Presmyk
Agency Name
University of California San Diego
Contact Types
Lead/Public Agency

Location

Cities
La Jolla
Counties
San Diego
Cross Streets
10 miles N.E. of the UCSD main campus, 1,800 ft East of I-15, just south of Pomerado Rd
Total Acres
approx. 2
State Highways
I-15
Railways
NCTD Coaster & Amtrack
Airports
MCAS Miramar
Waterways
Carrol Creek
Base
Poway

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes